Project Sentinel Weekly · July 13–19 (Week 4)

Scan, Reconstruct, Sleep, Repeat

Aditya NagachandraAditya Nagachandra Friday, July 17, 2026 ·3 min read

Week 4 was about wall framing. Crew was on site Tuesday through Saturday (off Monday and Sunday), and the extension went from bare perimeter framing to roof-arch joists going in by the end of the week.

Tuesday (7/14) — perimeter vertical framing for the new extension wrapped up, along with the diagonal joists.

Wednesday (7/15) — the big day: a framing package delivered mid-morning (wall columns, braces, ceiling/roof joists), and by end of day vertical framing, wind braces, and top plates were up across about half the extension.

Thursday (7/16) — mostly material movement and layout, shifting lumber from the front of the house back to the new zone, plus a bit of demo on the existing roof to tie the new addition in.

Friday (7/17) — another delivery (wall sheathing, sill plates), more ceiling joists and sheathing going up, and the crew briefly scaled up to three for a few hours.

Saturday (7/18) — a shorter half-day wrapping up roof-arch and extension-area joists. First Saturday the crew’s worked so far.

What this week actually cost

Every log doubles as a cost record. Take Week 4 (Jul 13–19) as a clean example: 5 active days, one crew, one invoice.

$3,500
paid for labor, Week 4
$54/hr
blended rate — 65h 05m of person-hours logged
58%
of the 8 AM–7 PM window actually worked
Tue 7/14
7h 5m
Wed 7/15
8h 20m
Thu 7/16
7h 5m
Fri 7/17
5h 55m
Sat 7/18
3h 45m

And the obligatory site blooper: the whole crew, breakfast, mid-build.

The crew — Sasha, Aditya, and the workers — having breakfast on site inside the framed extension, shot on a fisheye lens.
Breakfast with the crew!

More to come — this post will get filled out further before next week.